Risk register template

Each risk with likelihood, impact, score, mitigation, owner and status, sorted so the biggest risks get attention.

Use this templateFree, opens in your browser. No sign-up.

Risk register template
#
Risk
Likelihood (1–5)
Impact (1–5)
Score
Mitigation
Owner
Status
R1
Key engineer leaves mid-project
2
5
10
Pair on critical modules, document
Tech lead
Open
R2
Vendor API not ready in time
4
4
16
Build against a mock, weekly vendor check-in
PM
Watching
R3
Scope creep from stakeholders
4
3
12
Change requests go through the sponsor
PM
Open
R4
Data migration errors
3
4
12
Dry runs on a copy, rollback plan
Data eng
Open
R5
Security review delays launch
2
3
6
Book review 4 weeks early
Security
Closed
Score = likelihood × impact. 15+ red: act now · 8–14 amber: plan · < 8 green: monitor
Risk register
The risk register template as it opens in Kelvo: 1 sticky note and 1 table.

What's on the board

Table columns: #, Risk, Likelihood (1–5), Impact (1–5), Score, Mitigation, Owner, Status.

  • Score = likelihood × impact. 15+ red: act now · 8–14 amber: plan · < 8 green: monitor

How to use this template

  1. Click Use this template. It opens in the Kelvo app as a new board, saved in your browser.
  2. Double-click any box to change its text. Replace the examples with your own content.
  3. Paste a table. Paste comma- or tab-separated text and it becomes a table. Tab moves to the next cell and adds rows as you go.
  4. Add the next step with Tab. Select a box and press Tab: a new box appears, already linked. Type its label and press Enter.
  5. Present it. Frames become slides when you present, and the laser pointer helps you walk people through the board.

Good for

  • risk register
  • risk management
  • project manager
  • mitigation
  • raid
  • Kicking off a project with shared scope and roles
  • Tracking risks and milestones in one place
  • Reporting status to stakeholders

Related templates

  • Gantt chart (project timeline) template previewGantt chart (project timeline)

    Tasks as bars across ten weeks, coloured by phase, with the launch milestone — a quick project schedule.

  • Project charter template previewProject charter

    Purpose, objectives, scope in and out, deliverables, milestones, budget, team and risks — the one page to approve a project.

  • RACI matrix template previewRACI matrix

    Who is Responsible, Accountable, Consulted and Informed for each activity — ends the 'I thought you were doing it'.

  • Work breakdown structure (WBS) template previewWork breakdown structure (WBS)

    Break a project into phases and work packages small enough to estimate, assign and track.

  • Stakeholder map (power / interest) template previewStakeholder map (power / interest)

    Place stakeholders by power and interest to decide who to manage closely, keep satisfied, keep informed or monitor.

  • Project status report template previewProject status report

    A weekly RAG status: schedule, budget and scope at a glance, workstream status, highlights, risks and decisions needed.

All project management templates · All templates

Use the risk register template