PERT chart (critical path) template

Tasks as a network with durations, early start and finish, slack, and the critical path highlighted in red.

Use this templateFree, opens in your browser. No sign-up.

PERT chart (critical path) template
Start
A Requirements
5 d · ES 0 · EF 5
B UX design
8 d · ES 5 · EF 13
C API design
4 d · ES 5 · EF 9
D Backend build
18 d · ES 9 · EF 27
E Frontend build
12 d · ES 13 · EF 25
F Integration test
5 d · ES 27 · EF 32
G Docs & training
6 d · ES 25 · EF 31
H Launch
1 d · ES 32 · EF 33
Done · day 33
Task
Duration
Depends on
Early start–finish
Slack
A Requirements
5 d
—
0–5
0 (critical)
B UX design
8 d
A
5–13
1 d
C API design
4 d
A
5–9
0 (critical)
D Backend build
18 d
C
9–27
0 (critical)
E Frontend build
12 d
B
13–25
1 d
F Integration test
5 d
D, E
27–32
0 (critical)
G Docs & training
6 d
E
25–31
1 d
H Launch
1 d
F, G
32–33
0 (critical)
Critical path: A → C → D → F → H = 33 working days. Any slip there moves the launch; B, E and G have 1 day of slack.
PERT chart
The PERT chart (critical path) template as it opens in Kelvo: 10 boxes, 1 sticky note, 1 table and 11 links.

What's on the board

Table columns: Task, Duration, Depends on, Early start–finish, Slack.

  • B UX design 8 d · ES 5 · EF 13
  • E Frontend build 12 d · ES 13 · EF 25
  • G Docs & training 6 d · ES 25 · EF 31
  • Done · day 33
  • Start
  • A Requirements 5 d · ES 0 · EF 5
  • H Launch 1 d · ES 32 · EF 33
  • C API design 4 d · ES 5 · EF 9
  • D Backend build 18 d · ES 9 · EF 27
  • F Integration test 5 d · ES 27 · EF 32
  • Critical path: A → C → D → F → H = 33 working days. Any slip there moves the launch;…

How to use this template

  1. Click Use this template. It opens in the Kelvo app as a new board, saved in your browser.
  2. Double-click any box to change its text. Replace the examples with your own content.
  3. Paste a table. Paste comma- or tab-separated text and it becomes a table. Tab moves to the next cell and adds rows as you go.
  4. Add the next step with Tab. Select a box and press Tab: a new box appears, already linked. Type its label and press Enter.
  5. Present it. Frames become slides when you present, and the laser pointer helps you walk people through the board.

Good for

  • pert chart
  • critical path
  • network diagram
  • scheduling
  • project manager
  • Kicking off a project with shared scope and roles
  • Tracking risks and milestones in one place
  • Reporting status to stakeholders

Related templates

  • Gantt chart (project timeline) template previewGantt chart (project timeline)

    Tasks as bars across ten weeks, coloured by phase, with the launch milestone — a quick project schedule.

  • Project charter template previewProject charter

    Purpose, objectives, scope in and out, deliverables, milestones, budget, team and risks — the one page to approve a project.

  • RACI matrix template previewRACI matrix

    Who is Responsible, Accountable, Consulted and Informed for each activity — ends the 'I thought you were doing it'.

  • Risk register template previewRisk register

    Each risk with likelihood, impact, score, mitigation, owner and status, sorted so the biggest risks get attention.

  • Work breakdown structure (WBS) template previewWork breakdown structure (WBS)

    Break a project into phases and work packages small enough to estimate, assign and track.

  • Stakeholder map (power / interest) template previewStakeholder map (power / interest)

    Place stakeholders by power and interest to decide who to manage closely, keep satisfied, keep informed or monitor.

All project management templates · All templates

Use the PERT chart (critical path) template